NirmanSetu OSRCC Edition v2.6
End-to-End RCC House Construction SOP

8-Phase Construction & Quality Checklist

Toggle sub-tasks to simulate live site progress. Proper water curing after every concrete casting & plastering job is enforced.

Completion

63% (19/30 tasks)

1. Planning & Legal Approvals

Completed

Soil bearing test, structural blueprint, Municipality/Gram Panchayat sanction & BOQ budget

4/4 Steps₹1.45L Released

2. Site Preparation

Completed

Plot clearing, lime-powder layout marking, temporary store room & submersible boring

3/3 StepsIncluded in Phase 1

3. Foundation Work

Completed

Footing excavation, brick soling, PCC bed, steel cages & backfilling

4/4 Steps₹3.20L Released

4. Plinth Level Work

Completed

Tie/grade plinth beams, anti-termite & Damp Proof Course (DPC), interior sand filling

3/3 Steps₹2.60L Released

5. Superstructure Work (Active)

In Progress

10ft Columns, 10"/5" Brickwork, Lintel/Sunshade, Roof Shuttering, Conduits & M25 Roof Casting

4/5 Steps₹5.40L In Escrow (Curing)

6. Finishing & Utility Work

In Progress

Door/window frames, concealed electrical/plumbing chasing, plastering, parapet & Jalchhad

1/4 StepsUpcoming Milestone

7. Flooring, Painting & Fittings

Pending

Vitrified/marble tiles, window grills & shutters, putty/paint, sanitary & septic/overhead tank

0/5 StepsUpcoming Milestone

8. Final Handover

Pending

Deep site cleaning, permanent WBSEDCL electricity meter, municipal water & key handover

0/2 StepsFinal 5% Retention