Rajpur Sonarpur, South 24 Parganas • 1,150 Sq.Ft G+1 Provision RCC Roof Structure
₹5.40L Locked in Roof Curing Escrow
Shuttering removal safe after Day 14
Rajmistri, Dhalai Mistri & Helpers
8-Stage RCC House Construction Roadmap
Click any phase to inspect tasks, curing logs & site photos
Soil bearing test, structural blueprint, Municipality/Gram Panchayat sanction & BOQ budget
Plot clearing, lime-powder layout marking, temporary store room & submersible boring
Footing excavation, brick soling, PCC bed, steel cages & backfilling
Tie/grade plinth beams, anti-termite & Damp Proof Course (DPC), interior sand filling
10ft Columns, 10"/5" Brickwork, Lintel/Sunshade, Roof Shuttering, Conduits & M25 Roof Casting
Door/window frames, concealed electrical/plumbing chasing, plastering, parapet & Jalchhad
Vitrified/marble tiles, window grills & shutters, putty/paint, sanitary & septic/overhead tank
Deep site cleaning, permanent WBSEDCL electricity meter, municipal water & key handover
Digital Agreement & Design Vault
Customize construction terms, generate dual-signed PDF agreements sent to both Customer & Contractor emails, and upload sanctioned floor plans.
Turnkey_RCC_Agreement_v2.pdf
Dispatched to Customer & Contractor Emails
Panchayat_Sanctioned_Plan_G1.dwg
1,150 Sq.Ft • Structural Column Layout
Escrow Payment Gateway & Digital Payment Book
Milestone-linked payments protected until stage completion & curing verification
| Txn ID | Date | RCC Construction Milestone | Gateway Mode | Amount (INR) | Status |
|---|---|---|---|---|---|
| TXN-8801 | 10 Oct 2026 | Stage 1-2: Soil Test, Plan Sanction & Layout | Escrow UPI / RTGS | ₹1,45,000 | Released |
| TXN-8814 | 24 Oct 2026 | Stage 3: Excavation, Soling, PCC & Footing | Escrow Bank Transfer | ₹3,20,000 | Released |
| TXN-8829 | 06 Nov 2026 | Stage 4: Plinth Beam, DPC & Sand Filling | Escrow Bank Transfer | ₹2,60,000 | Released |
| TXN-8842 | 20 Nov 2026 | Stage 5: Columns, Brickwork & M25 Roof Casting | Escrow Hold (Curing) | ₹5,40,000 | Escrow Locked |
| TXN-8860 | Upcoming | Stage 6-7: Plastering, Jalchhad, Tiles & Fittings | Pending Milestone | ₹4,85,000 | Scheduled |